Pont fissuré à Colobane
Detailed report sheet

ANACIM
Khountou score
62/100To improve
Response rate
69%
Average processing time
5.6 days
Published responses
88
Reports followed
118
- Status
- Pending
- Priority
- Medium
- Category
- Bridges
- Location
- Colobane, Dakar
- Report date
- 19 April 2025 – 01:23
- Views
- 69
- Followers
- 6
- Resolution time
- In progress
- Reference
- #ANACIM-2025-2170
Main photoReport summary
Pont fissuré à Colobane. Les riverains signalent la situation depuis plusieurs jours et demandent une intervention rapide.
Le signalement a été transmis à ANACIM via la plateforme Khountou.
Report timeline
Report received
19 April 2025 – 01:23
Precise location
Colobane, Dakar
Colobane, Dakar
Observed issues
- Accidents fréquents signalés
- Véhicules endommagés
- Chaussée impraticable en saison des pluies
- Absence de balisage
Response from the administration (ANACIM)
The administration has not published a response yet.
Corrective actions taken
No corrective action published yet.