Recurring water cuts in Dakar: where do things stand in 2025?

This page presents the recommendations drawn from the citizen analysis, the data collected and the institutional responses.

  • Published on 15 May 2025
  • Updated: 23 May 2025
  • By Khountou editorial team
  • 11.6k views
  • 24 comments
  • 2.7k followers
Follow the case
Recommendations in total
24
Priority actions identified
8
Administrations concerned
6
Implementation horizon
6 – 18 months

Priority recommendations

  1. Urgently rehabilitate the oldest pipes to reduce leaks and bursts.
  2. Strengthen preventive maintenance and the rapid-response capacity of technical teams.
  3. Publish a provisional schedule of cuts by area and stick to it.
  4. Improve information and communication to citizens before, during and after cuts.

Recommendations by area

  • Infrastructure

    • Renew old pipes with a high leak rate.
    • Modernise pumping and treatment stations.
    • Deploy real-time pressure and leak sensors.
    • Secure the power supply of critical facilities.
  • Governance & coordination

    • Create a permanent Dakar Water coordination unit.
    • Better plan works with local authorities and utilities.
    • Strengthen coordination between SONES, SDE and local authorities.
    • Ensure regular accountability on commitments.
  • Citizen communication

    • Announce planned cuts 48 hours in advance.
    • Use SMS, social networks, radio and local posters.
    • Set up a free hotline and a dedicated chatbot.
    • Share water-saving and hygiene advice.
  • Monitoring & transparency

    • Publish key indicators: duration, frequency, affected areas.
    • Keep an open performance dashboard up to date.
    • Involve citizens in monitoring projects and commitments.
    • Make audit and evaluation reports public.

Recommended action plan

Recommended action plan
No.ActionResponsiblePriorityTarget dateRecommended status
1Rehabilitate the oldest pipes (phases 1 & 2)SONES / SDEHighQ2 2025To launch
2Set up systematic preventive maintenanceSONESHighQ3 2025In progress
3Roll out a schedule of cuts by areaSONES / SDEHighQ2 2025To launch
4Roll out a multichannel information systemSONES / SDEMediumQ3 2025In progress
5Improve the management of stocks and spare partsSONESMediumQ4 2025Planned
6Improve pressure in high-lying areasSONES / SDEMediumQ1 2026Planned

What citizens are asking for

  • Real-time and reliable information on cuts.
  • Fast and lasting repairs of leaks.
  • Fewer and shorter cuts.
  • Publication of progress and commitments kept.
Back to the case file