Sunday, 4 October 2026
KHOUNTOU.SNEvery citizen, an inspector

Pont fissuré à Yoff

Detailed report sheet

ANACIM

ANACIM

Khountou score

62/100To improve
  • Response rate

    69%

  • Average processing time

    5.6 days

  • Published responses

    88

  • Reports followed

    118

Status
Pending
Priority
Medium
Category
Bridges
Location
Yoff, Dakar
Report date
19 January 2025 – 11:30
Views
25
Followers
2
Resolution time
In progress
Reference
#ANACIM-2025-1967
Pont fissuré à YoffMain photo

Report summary

Pont fissuré à Yoff. Les riverains signalent la situation depuis plusieurs jours et demandent une intervention rapide.

Le signalement a été transmis à ANACIM via la plateforme Khountou.

Report timeline

  1. Report received

    19 January 2025 – 11:30

Precise location

Yoff, Dakar
Yoff, Dakar

View on the map

Observed issues

  • Accidents fréquents signalés
  • Véhicules endommagés
  • Chaussée impraticable en saison des pluies
  • Absence de balisage

Response from the administration (ANACIM)

The administration has not published a response yet.

Corrective actions taken

No corrective action published yet.

Photos / evidence

  • Evidence photo 1
  • Evidence photo 2
  • Evidence photo 3

Similar reports

  1. 1.
    Pont fissuré à Medina

    04 May 2025 – In progress

  2. 2.
    Pont fissuré à Colobane

    19 April 2025 – Pending

View all similar reports

Related documents

No related document.

View all documents