All reports addressed to the administration
Browse the citizen reports addressed to SENELEC, with their status, priority and follow-up.

SENELEC
Khountou score
82/100Excellent
Response rate
84%
Average processing time
2.8 days
Published responses
287
Reports followed
142
Reports received
142
+9 this month
Resolved
84
59% of total
In progress
42
30% of total
Critical
9
6% of total
| Report | Location | Date | Category | Status | Priority | Follow-up | Action |
|---|---|---|---|---|---|---|---|
![]() Branchement en attente depuis 4 mois à Sébikotane #SENELEC-2024-1806 | Sébikotane, Rufisque | 20 November 2024 21:36 | Connection delay | Resolved | Low | 59 6 | View report |
![]() Branchement en attente depuis 4 mois à Mbao #SENELEC-2024-1764 | Mbao, Pikine | 05 November 2024 03:27 | Connection delay | Resolved | Medium | 23 2 | View report |
![]() Branchement en attente depuis 4 mois à Diamniadio #SENELEC-2024-1701 | Diamniadio, Rufisque | 13 October 2024 00:15 | Connection delay | Resolved | Medium | 59 6 | View report |
![]() Branchement en attente depuis 4 mois à Mermoz #SENELEC-2024-1582 | Mermoz, Dakar | 30 August 2024 07:31 | Connection delay | Resolved | Medium | 33 3 | View report |
![]() Branchement en attente depuis 4 mois à Khombole #SENELEC-2024-1568 | Khombole, Thiès | 25 August 2024 02:08 | Connection delay | Resolved | Medium | 55 6 | View report |
![]() Branchement en attente depuis 4 mois à Saly #SENELEC-2024-1561 | Saly, Mbour | 22 August 2024 19:26 | Connection delay | Resolved | Medium | 65 7 | View report |
Reports by status
142Total
- Resolved84 (59%)
- In progress42 (30%)
- Pending13 (9%)
- Rejected3 (2%)
Most reported areas
- 1.Dakar64(45%)
- 2.Pikine31(22%)
- 3.Guédiawaye17(12%)
- 4.Rufisque13(9%)
- 5.Thiès10(7%)
Most followed reports
View all the most followed reports